| By
definition, a circuit breaker timing test is the process
of measuring the mechanical operating times with the goal
of verifying, analyzing and validating the proper function
of the circuit breaker. The
importance of timing tests is particularly critical in
maintaining the reliability of the transport and distribution
network, and also in the safety of the personnel employed
to maintain and operate the network protection apparatus.
Using
test execution and analysis tools, such as the
CBA-32P,
by Zensol, which is driven by the
CBA Win© software,
and with the experience acquired in the field, it is possible
to determine, with remarkable accuracy, the nature of
the problems that affect circuit breaker performance even
before disassembling the apparatus.
However,
timing tests are not limited to tests conducted after
the circuit breaker fails (corrective maintenance). In
the preventive maintenance strategy, the breaker is subject
to regular timing tests to detect trends in the degradation
and aging of the equipment, so that corrective action
may be applied before the problems become a danger to
the network or to the personnel.
Timing
tests are also useful in the factory to check production
quality standards, for reliability testing, to determine
the reference parameters, and for field testing after
the installation of a new circuit breaker.
|
Get this article in PDF format!

|
|
Consequences
of circuit breaker misoperation The
potential for damage that a circuit breaker – essentially
a protective device – can inflict on a network if
its operation is not within specifications are not to
be neglected. The economic repercussions can be just as
severe: cost of repairs, cost of the failure, interruption
of service to customers, etc.
If
the operation time during a Trip is too long, the short-circuit
current being interrupted will persist for much longer,
and could damage transformation, transmission and distribution
installations. The reduction of the interrupting time
can also bring the added benefit of increasing the transportable
power because the stable power limit increases in inverse
proportion with the tripping time. Also, the contacts
themselves are subject to the arc for longer periods,
which reduces their useful lifespan.
Also,
all contacts must be synchronized, within a certain tolerance
limit. In three-phase systems, not only must the contacts
in a single pole operate simultaneously, but all poles
must also operate at the same time.
If
the contacts in one pole do not operate synchronously,
then the slowest contact to close and the quickest to
open will absorb the greater part of the load, which will
cause the premature wear of the contacts in question.
The
difference between phases (poles) could generate voltage
spikes because of the very nature of the transportation
system, long transmission lines with extremities whose
state cannot always be predicted: open-ended, loaded,
capacitive or inductive load, etc. These factors may cause
huge voltage spikes that could potentially damage the
network and its equipment.
Inoperative
insertion resistors will cause premature wear on the main
contacts, since they will be subjected to the strongest
breaking currents, with the accompanying arc that will
be so much more powerful. Voltage surges will also be
present which can damage the breaker and surrounding equipment.
|
Back to top |
|
Troubleshooting
breakers The
first prerequisite for diagnosing breaker troubles is
to know the breaker being analyzed. Knowing the configuration
of the suspect apparatus’ innards, it is possible
to figure out the nature of the problem by visualizing
the mechanical process of the operation, in perspective
with the data of the timing test.
The
same is true of the experienced mechanic who can determine,
at a glance, the source of the mechanical problem in a
car. He knows not only automobile mechanics as a general
subject, but he knows the peculiarities of the model that
is brought to him.
One
also needs precise timing test data, such as those produced
by CBA Win© after a timing test conducted with
Zensol's CBA-32P.
The
following examples, showing the curves generated by the
faulty apparatus, followed by the analysis, the description
of the actions and corrections applied, and the curves
generated by the repaired equipment, illustrate how the
principles previously explained can be applied in a real-world
situation.
|
Back to top |
|
Conclusion The
role played by the high voltage circuit breaker has always
been one of the most determining factors of high voltage
network reliability. Its main role is to protect the network
and installed electric equipment from destructive short-circuit
current surges. A high voltage circuit breaker can stay
in the closed position for years but is still expected
to interrupt a powerful short-circuit current of many
thousands of amperes in a fraction of a second. The nature
of its operation places it among the most unpredictable
equipment on the electric network.
|
Back to top |
|
PK
– Inoperative resistor The
insertion resistor does not work. The spring on the moving
contact is broken and blocks the piston.

|
Back to top |
|
PK
– Correction
Disassembly
of the auxiliary moving contact, observe the damage (broken
spring), replacement of the spring and reassembly. A timing
test shows the return of the resistor’s trace on
the second phase (C02).

|
Back to top |
|
PK
– Rebounds
Abnormal
rebounds on an auxiliary (resistive) contact. The head
on the semi-mobile contact is loose.

|
Back to top |
|
PK
– Correction Disassembly
of the auxiliary moving contact, observe the problem (loose
head). Tighten the head and immobilize with Loctite and
punching, followed by reassembly. A timing test shows
the disappearance of the unusual rebounding on the resistive
trace.

|
Back to top |
|
Dead
Tank – Missing main contact
Case
of an inoperative main contact on one phase (PhB), showing
an open circuit on a Close operation.

|
Back to top |
|
Dead
Tank – Correction Disassembly
of the internal parts of the defective phase. Observe
the damage, a shaft connecting the actuating rod to the
moving contact had fallen, causing the contact piston
to separate from the actuating rod. Replace the shaft
and reassemble. A timing test shows the reappearance of
the main contact on the second phase.

|
Back to top |
|
PK
– Valve in wrong position
The
close control valve on the breaker is in the wrong position.
The result is that the closing times on the two chambers
connected to this valve are longer than the others.

|
Back to top |
|
PK
– Correction Disassembly
of the close control valve. Observe that the body of the
valve had been installed at a 90o angle relative to the
normal position of the valve body, which caused a delay
in the admission of compressed air, producing the observed
delays on the signals of contacts A-1 and A-2. Replace
the valve in the correct position. A timing test shows
that contacts A-1 and A-2 now close within the expected
times.

|
Back to top |
|
SF6
breaker with hydraulic commands - adjustment screw incorrectly
set An
adjustment screw on the breaker is incorrectly set, creating
a 25 millisecond difference on one phase. This problem
may produce similar results to those produced by an incorrectly
positioned control valve.

|
Back to top |
|
SF6
breaker with hydraulic commands – Adjustment screw
– Correction The
adjustment screw was set to obtain similar closing times
on all phases and contacts. A timing test shows that the
closing time on contacts C03 and C04 are now comparable
to those on the other contacts.

|
Back to top |
|
SF6
breaker with hydraulic actuator – short-circuit
time
Adjustment
of the short-circuit time for a SF6 breaker with hydraulic
actuator. Circuit breakers with hydraulic actuators are
usually equipped with a signal piston with drives the
signaling contacts. These contacts control the minimum
short-circuit time of the circuit breaker (trip-free).
This example shows all three phases following a Close-Open
operation. It may be seen that the short-circuit time
of Phase C is longer than the others. This requires adjustment
of the restrictions of the command lines of the signal
piston.

|
Back to top |
|
SF6
breaker – Correction of short-circuit time Adjust
the admission restriction of the hydraulic command in
order to obtain synchronous operation of all phases.

|
Back to top |
|
Pneumatic
breaker, isolation time
Air-driven
breakers are usually equipped with a pneumatic inverter
switch on each phase. The main function of this switch
is to prevent the close operation for approximately 250
milliseconds after a trip, so the dielectric medium has
time to properly regenerate. The following example shows
all three phases after an Open-Close operation (the close
order is maintained until the end of the recording). It
is clear that the switch on Phase B much quicker than
the two other phases, which requires an adjustment.

|
Back to top |
|
Pneumatic
breaker – Correction
Adjust
the restriction on the inverter switch in order to obtain
comparable times between all phases.

|
Back to top |
|
Shielded
breaker Two
problems are noted on this breaker. First, the engagement
piston doesn't attain its full travel (180 mm).
Second, the piston begins moving 30 to 35 milliseconds
after the main pistons. The normal delay is about 20 milliseconds.

|
Back to top |
|
Shielded
breaker – Correction
To
correct the delay problem, the diameter of the appropriate
diaphragm orifice is increased by 0.020 inches. The premature
reopening of the resistor is due to the main contact closing
later. The curve shows that there is also a problem with
the upper piston (DpC) of the main contact on Phase C.
This piston was overhauled prior to the timing test.

|
Back to top |
|
Dead
Tank – Bad damping The
following timing diagram shows a hard rebound at the bottom
of the displacement curve, during a Trip operation on
a Dead Tank type circuit breaker. This suggests a lack
of damping at the end of travel. Excess energy is poorly
absorbed and damage may already have occurred.

|
Back to top |
|
Dead
Tank – Correction After
examining the internal components, it is observed that
damage has indeed occurred on the main rod of the moving
contact. The source of the problem is a defective dashpot.
After repair, the timing test shows correct damping at
the bottom of the travel curve.

|
Back to top |
|
2.
The distribution network At
the output of the generating stations, transforming stations
step up the production-level voltage to the high voltage
necessary to efficiently carry the electricity over longer
distances.
The
power transmission lines are made of conductors such as
overhead lines or underground cables. In spite of their
apparent simplicity, these conductors conceal important
influencing factors to the electricity transmission network.
|